Noble Helium told the Australian Securities Exchange on 25 November 2026 that its drilling rig and mast had cleared customs at the Kenya–Tanzania border and were on their way to Kinambo-1. The company still expected to begin drilling before the end of November, though the equipment had yet to be assembled and commissioned at the site.
Kinambo-1 is now the only well Noble has committed to drill in this campaign at its wholly owned North Rukwa project in south-west Tanzania. Its results will guide the decision on a second well. Funding is a separate constraint: at 30 September, Noble reported enough cash to cover 1.61 quarters of outgoings at the September quarter’s spending rate, when mobilisation had been paused to conserve cash.
What one deeper well can establish
In May, Noble planned two wells on the project’s western margin, targeting depths of about 430 metres and 1,500 metres, with drilling to start in early July. By September, the company was targeting early October. On 13 November, it set out a revised plan: drill Kinambo-1 to 1,850 metres and proceed with a second well “only if required,” depending on the first well’s results.
Noble said the deeper well would avoid moving the rig between sites and allow its logging contractor, SLB, to collect a complete set of subsurface measurements for an independent resource assessment. The company attributed the more recent delays to the contractor’s availability and the 1,500-kilometre road journey from Kenya. The well pad, access roads and camp had been completed and certified in September.
The first results may show what the well contains without showing how much gas it can deliver. In 2023, Noble’s Mbelele wells recovered fluid samples at depths of 213 to 453 metres. Gas released from those samples contained 0.4% to 2.46% helium, with the balance mostly nitrogen. Those measurements established the presence of helium, not a commercial flow rate.
At Kinambo-1, Noble plans to collect downhole samples for on-site analysis and laboratory verification. Those results and SLB’s measurements will feed into the independent reserves and resources certification Noble is targeting for the first half of 2027. Whether the well is prepared for a later production test depends on the results.
A prospective resource is not a sales forecast
Independent assessor NSAI put North Rukwa’s best-estimate prospective helium resource at 118 billion cubic feet. That is not a reserve: commercial production has not been demonstrated. Noble’s shares closed at A$0.025 on 24 November, giving the company a market value of about A$31 million. Subtracting its A$3.9 million in September cash and adding A$1.2 million in drawn loans gives an enterprise value of roughly A$28 million, or US$18 million at the exchange rate used in Noble’s investor presentation.
That works out to about 16 US cents per thousand cubic feet of estimated helium in the ground. By contrast, the US Geological Survey put the 2025 US base price for processed Grade-A helium at about US$330 per thousand cubic feet before surcharges. The figures measure different things: Noble would need to establish recoverable volumes, finance production and secure buyers before it could earn revenue from the gas.
Noble’s April presentation assumed a long-term bulk price of US$450 per thousand cubic feet. Its headline estimate of US$50 billion to US$100 billion or more in unrisked gross resource value used post-shortage spot prices and assumed 50% recovery. Applied to the 225.5-billion-cubic-foot mean resource estimate, rather than the lower best estimate, the two ends of that range imply prices of roughly US$443 and US$887 per thousand cubic feet. Neither figure accounts for development costs or the time needed to sell the gas. For scale, the USGS estimated total world helium production in 2025 at about 6.7 billion cubic feet.
Cash needs precede any production revenue
Noble had no undrawn credit facilities at 30 September. Outgoings were A$2.4 million in the September quarter even with the rig stood down, so the reported 1.61 quarters of funding is not a forecast of how long cash will last once drilling begins. Noble’s auditor flagged a material uncertainty over its ability to continue as a going concern.
The company also faces a disputed A$4.0 million claim from P R Marriott Drilling relating to the 2023 campaign and the removal of that rig from Tanzania. Noble is defending the claim and counterclaiming for delay costs. It argues that the net amount is A$655,141 in its favour; that is Noble’s position, not a settlement.
Noble raised A$12 million in April at A$0.029 a share, a 40.8% discount to the previous close. Its share count rose from 599.5 million in April to 1.32 billion by 30 September. The 24 November closing price was below the April issue price.
If Kinambo-1 succeeds, Noble’s plan calls for a small western-margin operation generating cash flow within 18 to 24 months. That timetable depends not just on the well result but also on resource certification, a sales agreement and financing for the plant. Clearing customs moved the rig closer to the site; it did not resolve those commercial questions.